The three views
| View | Best for | Watch out |
|---|---|---|
| Board | Work moving through states — the daily view. | Hides dates. A board looks healthy while everything is late. |
| List | Scanning, bulk editing, sorting by date or owner. | Loses the sense of flow. |
| Timeline | Seeing overlap and sequencing. | It is a view, not a planner. Moving a bar does not reschedule what follows. |
Website rebuild
34 tasks · 9 done · ends 30 April
Backlog12
In progress5
Review3
Done9
Setting one up
Not after the client or the quarter. "Website rebuild" tells you when it is finished; "Acme Q2" does not.
Board columns work when moving between them means something. "Design / Build / Content" is a category split and produces three parallel to-do lists.
Membership is per project. Somebody who is not a member does not see it in their lists.
A project with no end date never appears late.
See Portfolios.
Archiving
Finished projects are archived, not deleted. An archived project leaves the active lists, stops appearing in portfolio roll-ups, and remains fully searchable — which matters, because the comments on a finished project are usually the record of why something was done a particular way.
What this does not do
Duplication is the mechanism. There is no template gallery.
You cannot snapshot a plan and report against it.
Financials live in Accounting.
Moving one task does not move its successors.
Questions
Can a task belong to two projects?
No. One project per task.
Can we reorder sections?
Yes.
Who can archive a project?
Project members. It is reversible.